模拟试题(一)下

21. Activity duration estimate inputs include all of the following except:
a. Resource requirements.
B. Basis of estimates.
C. Activity lists.
D. Constraints.

22. All of the following are contract types except:
a. Unit-price.
B. Make-or-buy.
C. Cost reimbursable.
D. Lump sum.

23. Initiation inputs for a project include all of the following except:
a. Product description.
B. Strategic plan.
C. Project charter.
D. Selection criteria.

24. Responses to risk threats include all of the following except:
a. Avoidance.
B. Acceptance.
C. Mitigation.
D. Rejection.

25. The process of performance reporting includes all of the following 
except _____________.
A. Status reporting.
B. Progress reporting.
C. Forecasting.
D. Product analysis

26. Constrained optimization methods of project selection include:
a. Scoring models. 
B. Benefit-cost ratios. 
C. Multi-objective programming algorithms.
D. Subjective analyses.

27. Which of the following statements concerning contract type is correct?
A. A fixed price contract contains the most risk for the buyer.
B. Cost reimbursable contracts offer sellers the highest profit potential.
C. Lump sum contracts offer sellers the greatest profit potential.
D. Unit price contracts are illegal in many jurisdictions.

28. A Work Breakdown Structure (WBS) numbering system should allow project
 staff to:
a. Identify the level at which individual WBS elements are found.
B. Identify configuration management milestones.
C. Estimate the costs of WBS elements.
D. Provide project justification.

29. All of the following are true quality statements except:
a. Quality improvement depends upon better definition and increased awarene
ss of the
 requirements/specifications.
B. Project quality management must address both management of the project 
and the product of the
 project.
C. Recognition of key actions required of each team member is necessary to 
meet quality objectives.
D. Computer-aided design systems can improve quality, but only at the expense of an 
increase in the
 cost of design.

30. All of the following are examples of tools often used in cost 
estimating except:
a. Parametric modeling.
B. Analogous estimating.
C. Bottom-up estimating.
D. Activity duration estimates.

31. At XYZ Inc., the hourly wage for semi-skilled workers is $14.00. The annual audit shows that
 fringe benefits cost 30% of basic wages, and that overhead costs are 60% 
of wages plus fringe
 benefits. What is the loaded” hourly wage for a semi-skilled 
worker at XYZ Inc.?
A. $27.14.
B. $28.96. 
C. $30.03.
D. $29.12.

32. Of the following estimates, which most accurately reflect the actual
 cost of the project?
A. Conceptual estimates.
B. Order of magnitude estimates.
C. Preliminary estimates.
D. Bottom-up estimates.

33. The most crucial time for project risk assessment is:
a. When a problem surfaces.
B. During the planning phase.
C. During the close-out phase.
D. After the project schedule has been published.

34. When there is uncertainty associated with one or more aspects of 
the project, one of the first steps to take is to:
a. Revise project plan.
B. Conduct a risk-benefit analysis.
C. Conduct a needs analysis. 
D. Increase the estimated cost of the project.

35. Including a contingency reserve in the project budget is intended to:
a. Reduce the probability of scope changes.
B. Increase the probability of scope changes.
C. Reduce the probability of a cost overrun.
D. Increase the probability of a cost overrun.

36. Given the information in the following table, what is the expected 
value from this risk event?

Probability Result 
a. -10,000.
B. - 7,500.
C. + 2,500.
D. -7,000.

37. A contractor is working on a fixed price contract that calls for a 
single, lump sum payment upon
 satisfactory completion of the contract. About halfway through the 
contract, the contractor project
 manager informs their contract administrator that financial problems are
 making it difficult for
 them to pay their employees and subcontractors. The contractor asks for 
a partial payment for work
 accomplished. Which of the following actions by the buyer is most likely 
to cause problems for the
 project?
A. Starting partial payments for work accomplished.
B. Making no payments because it would violate the conditions of the 
contract.
C. Paying for work accomplished to date.
D. Negotiating a change to the payment conditions in the contract.

38. A precise description of a physical item, procedure, or service for 
implementation of an item or
 service is called :
a. Work package.
B. Baseline.
C. Product description.
D. Work breakdown structure (WBS) element.

39. A project should be terminated for all of the following reasons except:
a. Lack of team synergy.
B. The project no longer meets the company’s objectives.
C. The resources are not available to complete project activities.
D. Project funding has been significantly reduced.

40. One common way to compute estimated at completion (EAC) is to take
 the project budgeted-at-completion and:
a. Divide it by the schedule performance index.
B. Multiply it by the schedule performance index.
C. Multiply it by the cost performance.
D. Divide it by the cost performance index.
【作者:本站编辑┊来源:不详┊2006-05-27】TAGS:
评论与咨询 内容报错
姓名: 电话: 邮箱: 地址:

  • ·本咨询平台是部分培训机构与本站指定的网上报名、咨询的专用平台,您可以通过此处提交您的信息,我们或该机构会根据您所提交的信息及时给予回复;
  • ·为了更好的问您服务,请填写您真实的姓名和相关联系方式,以便我们能及时给您答复;
  • ·不得提交有关违反国家互联网规定的不良信息,对于违规者我们有权追究你的法律责任!若有任何问题请 联系我们
关于我们 | 服务条款 | 广告服务 | 客服中心 | 网站导航 - 设为首页 - 收藏本站
Copyright © 2006-2008 www.0510edu.com.cn All Rights Reserved
无锡培训资讯网 版权所有
Powered By:AspArticle2.0 在远方